Click on any project below to see more about each gallery.
1. Springfield works mill
3 stages of the hand demolition of a stone chimney over one hundred feet high that
was running along the side of a main railway line.
2. Washington Street & Whitley Bridge in Leeds
Recycling brick and concrete for re-use on site for the client Kendall Cross part of the Galliford Try group.
3. Whitby life boat station for HBG
Work was carried out to the satisfaction of HBG
and the RNLI.
4. Whitby Laundrette
GRP carried out the demolition work within Whitby Town Centre on behalf
of Siterite Builders, A local building contractor.
5. West Tanfield
Contracted by R&H building services, GRP carried out during three phases.
6. ESSO
GRP was sub-contracted by Fox Construction a repeat customer of GRP,
to carry out the demolition work and fuel storage tank removal of Fenton Service Station,
Rotherham.